Agree­ment No. CN005 — Fuel Farm Expan­sion
SEC­TION 00050
AGREE­MENT NO. CN005

THIS AGREE­MENT is made by and between Pana­ma City – Bay Coun­ty Air­port and Indus­tri­al Dis­trict (here­inafter called ​“Dis­trict”) d.b.a North­west Flori­da Beach­es Inter­na­tion­al Air­port (here­inafter called ​“ECP” or the ​“Air­port”), a spe­cial dis­trict with­in the State of Flori­da whose address is 6300 West Bay Park­way, Pana­ma City, Flori­da 32409, and Mor­gan Con­tract­ing, Inc. doing busi­ness as a Flori­da for prof­it Cor­po­ra­tion, hav­ing a busi­ness address of 900 Dutch Val­ley Dri­ve, Knoxville, Ten­nessee 37918 (here­inafter called ​“Con­trac­tor”), for the per­for­mance of the Work (as that terms is defined below) in con­nec­tion with the con­struc­tion of the Fuel Farm Expan­sion Project (“Project”), in accor­dance with the Draw­ings and Spec­i­fi­ca­tions pre­pared by AVCON, Inc., the Engi­neer of Record (here­inafter called ​“Engi­neer”) and all oth­er Con­tract Doc­u­ments here­after spec­i­fied, includ­ing as more par­tic­u­lar­ly described Bid num­ber ITB-2026 – 14 (“the Bid/​Solicitation”). Dis­trict and Con­trac­tor, for the con­sid­er­a­tion here­in set forth, agree as follows:

1. SCOPE OF WORK

The Con­trac­tor shall fur­nish, at its sole expense, all super­vi­sion, labor, equip­ment, tools, mate­r­i­al, and sup­plies to prop­er­ly and effi­cient­ly per­form all of the work required under the Con­tract Doc­u­ments and shall be sole­ly respon­si­ble for the pay­ment of all tax­es, per­mits and license fees, labor fringe ben­e­fits, insur­ance and bond pre­mi­ums, and all oth­er expens­es and costs required to com­plete such work in accor­dance with this Agree­ment (col­lec­tive­ly the ​“Work”). Contractor’s employ­ees and per­son­nel shall be qual­i­fied and expe­ri­enced to per­form the por­tions of the Work to which they have been assigned. Con­trac­tor shall per­form all work in a time­ly and pro­fes­sion­al man­ner in accor­dance with the require­ments of the con­tract doc­u­ments. Con­trac­tor acknowl­edges that the Dis­trict is rely­ing on Con­trac­tors rep­re­sen­ta­tions of its expe­ri­ence and capa­bil­i­ty to per­form such services/​goods in accor­dance with indus­try stan­dards of care and all con­tract require­ments. In per­form­ing the Work here­un­der, Con­trac­tor shall be an inde­pen­dent con­trac­tor, main­tain­ing con­trol over and hav­ing sole respon­si­bil­i­ty for Contractor’s employ­ees and oth­er per­son­nel. Nei­ther Con­trac­tor, nor any of Contractor’s sub-con­trac­tors or sub-sub­con­trac­tors, if any, nor any of their respec­tive employ­ees or per­son­nel, shall be deemed ser­vants, employ­ees, or agents of OWNER.

2. COM­PEN­SA­TION

As com­pen­sa­tion for the ser­vices con­tem­plat­ed here­in and per­for­mance ren­dered by the Con­trac­tor of its duties and oblig­a­tions here­un­der, Dis­trict shall pay Con­trac­tor accord­ing to the UNIT PRICE sub­mit­ted in response to the Bid, upon the suc­cess­ful com­ple­tion and inspec­tion as the same may be final­ly deter­mined by the District’s Exec­u­tive Direc­tor or his designee(s). The Exec­u­tive Direc­tor or his designee may vol­un­tar­i­ly divide pay­ment of the bid price into phas­es depend­ing on mile­stones of completion.

Unless express­ly stat­ed oth­er­wise, all prices are inclu­sive of all costs of per­form­ing the work (includ­ing but not lim­it­ed to labor, mate­ri­als, equip­ment use, trav­el, ship­ping, over­head, and prof­it). The Dis­trict ​’s oblig­a­tion to pay is con­tin­gent upon appro­pri­a­tion of funds for the applic­a­ble fis­cal year and the Contractor’s com­plete per­for­mance of the work (or spec­i­fied mile­stones, if any).

Con­trac­tor is respon­si­ble for pay­ing all applic­a­ble sales, con­sumer, use, and oth­er tax­es required by law, and such tax­es are deemed includ­ed in the con­tract prices unless stat­ed oth­er­wise. Contractor’s bid pric­ing is incor­po­rat­ed here­in as part of the con­tract doc­u­men­ta­tion for pay­ment pur­pos­es. No addi­tion­al com­pen­sa­tion shall be due for any work or mate­ri­als that are rea­son­ably infer­able from the express­ly described scope of work.

3. PAY­MENT

Invoic­ing: Con­trac­tor shall sub­mit invoic­es to:

ENGI­NEER OF RECORD

AVCON, Inc.

320 Bayshore Drive

Niceville, Flori­da 32578

Office: (850) 638‑0500

Mobile: (850) 890‑6983

Email: adykes@​avconinc.​com

SUB­CON­SUL­TANTS

UES (Geot­ech­ni­cal Testing)

South­east­ern Sur­vey­ing and Map­ping Cor­po­ra­tion (Sur­vey)

DIS­TRICT (COPY)

ATTN: Melanie Stone, Account­ing Department

6300 West Bay Park­way, Suite A,

Pana­ma City, Flori­da 32409

Office: (850) 636‑8950

Email: Accounting@​pcairport.​com

Invoic­es must ref­er­ence the Con­tract num­ber. Each invoice shall be item­ized and include suf­fi­cient detail (such as dates of ser­vice, descrip­tion of goods/​services, quan­ti­ties, unit prices, and extend­ed totals) to per­mit ver­i­fi­ca­tion by the Dis­trict. If the con­tract is deliv­er­ables-based or has pay­ment mile­stones, Con­trac­tor shall invoice only upon District’s accep­tance of the deliv­er­able or com­ple­tion of the mile­stone. No addi­tion­al charges of any kind will be allowed unless specif­i­cal­ly pro­vid­ed for in this Agree­ment. For exam­ple, freight, fuel sur­charges, han­dling fees, or trav­el costs are not sep­a­rate­ly payable unless explic­it­ly item­ized in the con­tract com­pen­sa­tion terms. Like­wise, sales tax­es are includ­ed in the con­tract price unless the Dis­trict pro­vides a sales tax exemp­tion cer­tifi­cate for cer­tain pur­chas­es (the Dis­trict is tax-exempt for direct pur­chas­es of goods, but Con­trac­tor is respon­si­ble for its own sales/​use tax on mate­ri­als unless uti­liz­ing District’s direct pur­chase pro­gram if offered).

Pay­ment Method: The Dis­trict will make pay­ment for approved invoic­es via ACH (Auto­mat­ed Clear­ing House) trans­fer or vir­tu­al cred­it card. The Dis­trict will not issue tra­di­tion­al paper checks unless oth­er­wise agreed. Con­trac­tor must pro­vide the nec­es­sary infor­ma­tion for ACH pay­ments or accept the District’s vir­tu­al card pro­gram. The Dis­trict is not respon­si­ble for any fees Con­trac­tor may incur from its bank or card proces­sor for receiv­ing pay­ment. Con­trac­tor agrees that no addi­tion­al con­ve­nience or pro­cess­ing fees shall be added to District’s invoic­es for uti­liz­ing the District’s elec­tron­ic pay­ment methods.

Pay­ment Sched­ule: The Dis­trict shall make pay­ment in accor­dance with the Flori­da Local Gov­ern­ment Prompt Pay­ment Act (F.S. 218.74). For con­struc­tion con­tracts, this process defined in Sec­tion 18 of the District’s Gen­er­al Con­di­tions, Sec­tion 00100 of the Bid. If an invoice is dis­put­ed, the Dis­trict will noti­fy Con­trac­tor of the issue and may with­hold the dis­put­ed por­tion of pay­ment pend­ing res­o­lu­tion. The Dis­trict may par­tial­ly pay an invoice for uncon­test­ed items and with­hold pay­ment only for the con­test­ed amount, if any, until res­o­lu­tion. Con­trac­tor agrees to not sus­pend per­for­mance over any pay­ment dis­pute pro­vid­ed the Dis­trict is mak­ing a good-faith effort to resolve the dispute.

Retainage (if applic­a­ble): Retainage is gov­erned by Sec­tion 18.1.4 of the District’s Gen­er­al Con­di­tions, Sec­tion 00100 of the Bid.

No Addi­tion­al Charges: No addi­tion­al charges of any kind will be allowed unless specif­i­cal­ly pro­vid­ed for in this Agree­ment. For exam­ple, freight, fuel sur­charges, han­dling fees, or trav­el costs are not sep­a­rate­ly payable unless explic­it­ly item­ized in the con­tract com­pen­sa­tion terms. Like­wise, sales tax­es are includ­ed in the con­tract price unless the Dis­trict pro­vides a sales tax exemp­tion cer­tifi­cate for cer­tain pur­chas­es (the Dis­trict is tax-exempt for direct pur­chas­es of goods, but Con­trac­tor is respon­si­ble for its own sales/​use tax on mate­ri­als unless uti­liz­ing District’s direct pur­chase pro­gram if offered).

4. TERM

This Agree­ment shall com­mence upon com­plete exe­cu­tion by the par­ties and con­tin­ue through Contractor’s final com­ple­tion of the work and the District’s accep­tance, plus any war­ran­ty peri­ods, unless ear­li­er ter­mi­nat­ed as pro­vid­ed here­in. Any spe­cif­ic dates or time­frames for com­ple­tion described in the Solic­i­ta­tion or Contractor’s pro­pos­al (such as a ​“Sub­stan­tial Com­ple­tion” or final com­ple­tion date) are incor­po­rat­ed as mile­stones. Time is of the essence in this Agree­ment. Con­trac­tor shall com­mence work with­in 10 days of issuance of the District’s notice to pro­ceed (if applic­a­ble) and shall achieve any stat­ed com­ple­tion dates.

In accor­dance with Flori­da law, the District’s per­for­mance and oblig­a­tion to pay under this Agree­ment is con­tin­gent upon an appro­pri­a­tion of funds by the Dis­trict Coun­cil. If funds are not appro­pri­at­ed or are with­drawn, the Dis­trict may ter­mi­nate the Agree­ment with­out penal­ty or fur­ther obligation.

5. TIME

Time is of the essence in this Agree­ment. The Con­trac­tor will com­mence the Work required by the Con­tract Doc­u­ments on the date indi­cat­ed on the Notice to Pro­ceed as issued by Own­er. Under no cir­cum­stances will Con­trac­tor begin work pri­or to issuance of a Notice to Pro­ceed. All costs incurred out­side the Con­tract Price pri­or to issuance of a Notice to Pro­ceed shall be borne sole­ly by Con­trac­tor. The expec­ta­tion for com­ple­tion shall be detailed in the issued Notice to Proceed.

Unex­cused delays in per­for­mance may con­sti­tute a breach of this Agree­ment. If Con­trac­tor antic­i­pates any delay in meet­ing a dead­line, it shall imme­di­ate­ly noti­fy the Dis­trict in writ­ing, explain­ing the cause and length of the delay and propos­ing a recov­ery plan. No exten­sion of time shall be effec­tive unless approved in writ­ing by the Dis­trict Exec­u­tive Direc­tor through a change order or amendment.

Con­trac­tor acknowl­edges and agrees that no inter­rup­tion, inter­fer­ence, inef­fi­cien­cy, sus­pen­sion or delay in the com­mence­ment or progress of the Work from any cause what­ev­er, includ­ing those for which the Own­er, Project Rep­re­sen­ta­tive, or Engi­neer may be respon­si­ble, in whole or in part, shall relieve Con­trac­tor of its duty to per­form or give rise to

Agree­ment No. CN005 — Fuel Farm Expansion

any right to dam­ages or addi­tion­al com­pen­sa­tion from Own­er. Con­trac­tor express­ly acknowl­edges and agrees that it shall receive no dam­ages for delay. Contractor’s sole rem­e­dy, if any, against Own­er will be the right to seek an exten­sion to the Con­tract Time; pro­vid­ed, how­ev­er, the grant­i­ng of any such time exten­sion shall not be a con­di­tion prece­dent to the afore­men­tioned ​“No Dam­age For Delay” pro­vi­sion. This sec­tion shall express­ly apply to claims for ear­ly com­ple­tion, as well as to claims based on late com­ple­tion. Notwith­stand­ing the fore­go­ing, if the Work is delayed due to the fault or neglect of OWN­ER or any­one for whom OWN­ER is liable, and such delays have a cumu­la­tive total of more than 90 cal­en­dar days, Con­trac­tor may make a claim for its actu­al and direct delay dam­ages accru­ing after said 90 cal­en­dar days as pro­vid­ed in the Sup­ple­men­tal Con­di­tions, Con­tract Claims and Changes. Except as express­ly set forth in this sec­tion, in no event shall Own­er be liable to Con­trac­tor whether in con­tract, war­ran­ty, tort (includ­ing neg­li­gence or strict lia­bil­i­ty) or oth­er­wise for any accel­er­a­tion, soft costs, lost prof­its, spe­cial, indi­rect, inci­den­tal, or con­se­quen­tial dam­ages of any kind or nature whatsoever.

The Con­trac­tor agrees to pay the Own­er, as liq­ui­dat­ed dam­ages, the sum of $500.00 for each con­sec­u­tive cal­en­dar day that expires after the Con­tract Time until Sub­stan­tial Com­ple­tion of the WORK is achieved.

6. COM­PLI­ANCE WITH LAWS

Con­trac­tor shall com­ply with all applic­a­ble fed­er­al, state, and local laws, reg­u­la­tions, ordi­nances, and codes in the per­for­mance of this Agree­ment. This includes, but is not lim­it­ed to, labor laws, envi­ron­men­tal laws, safe­ty reg­u­la­tions (e.g., OSHA stan­dards), immi­gra­tion laws (includ­ing the E‑Verify require­ment), and licens­ing laws rel­e­vant to Contractor’s busi­ness. Con­trac­tor must obtain and main­tain all nec­es­sary per­mits, licens­es, or cer­ti­fi­ca­tions required to per­form the work (e.g., busi­ness tax receipt, pro­fes­sion­al licens­es, con­struc­tion per­mits, envi­ron­men­tal per­mits). The costs of such com­pli­ance are includ­ed in the con­tract sum.

Con­trac­tor is respon­si­ble for ensur­ing that its employ­ees, sub­con­trac­tors, and agents are aware of and com­ply with all laws and reg­u­la­tions applic­a­ble to their activ­i­ties under this Agree­ment. This includes any Dis­trict-spe­cif­ic rules while work­ing on Dis­trict prop­er­ty (such as secu­ri­ty rules, traf­fic, and park­ing reg­u­la­tions, etc.).

7. PUB­LIC RECORDS RESPONSIBILITIES

Pub­lic Records Law: Con­trac­tor acknowl­edges that Florida’s Pub­lic Records Law (Chap­ter 119, F.S.) applies to this Agree­ment. Con­trac­tor shall: (a) keep and main­tain all pub­lic records required by the Dis­trict to per­form the ser­vices; (b) upon request from the District’s cus­to­di­an of records, pro­vide the request­ed records to the Dis­trict in a time­ly man­ner and in a for­mat com­pat­i­ble with the District’s infor­ma­tion sys­tems; © ensure that exempt or con­fi­den­tial records are not dis­closed except as autho­rized by law; and (d) upon com­ple­tion or ter­mi­na­tion of the con­tract, trans­fer all pub­lic records relat­ed to the con­tract to the Dis­trict, at no cost, or, if records are retained by Con­trac­tor, con­tin­ue to meet all legal require­ments for retain­ing pub­lic records. If Con­trac­tor trans­fers all records to the Dis­trict at con­tract com­ple­tion, Con­trac­tor shall destroy any dupli­cate con­fi­den­tial records upon such trans­fer. If Con­trac­tor keeps records, it shall main­tain them in accor­dance with applic­a­ble reten­tion sched­ules and make them avail­able to the Dis­trict upon request.

If Con­trac­tor fails to pro­vide pub­lic records when required, the Con­trac­tor may be sub­ject to penal­ties under Sec­tion 119.10, F.S. Addi­tion­al­ly, fail­ure to com­ply with these pub­lic records duties is a mate­r­i­al breach of this Agree­ment, which may result in imme­di­ate ter­mi­na­tion by the Dis­trict. Con­trac­tor shall indem­ni­fy and defend the Dis­trict for any costs, includ­ing attor­neys’ fees, incurred by the Dis­trict due to Contractor’s fail­ure to com­ply with pub­lic records dis­clo­sure requirements.

IF THE CON­TRAC­TOR HAS QUES­TIONS REGARD­ING THE APPLI­CA­TION OF CHAP­TER 119, FLORI­DA STATUTES, TO THE CONTRACTOR’S DUTY TO PRO­VIDE PUB­LIC RECORDS RELAT­ING TO THIS CON­TRACT, IT SHOULD CON­TACT PARK­ER J. MCCLEL­LAN, JR., EXEC­U­TIVE DIREC­TOR (CUS­TO­DI­AN OF PUB­LIC RECORDS) AT 6300 WEST BAY PARK­WAY, PANA­MA CITY, FL 32409, PHONE: 850−636−8950 EMAIL: INFO@​PCAIRPORT.​COM.

8. INSUR­ANCE AND INDEMNIFICATION

Con­trac­tor shall, at its own expense, pro­cure and main­tain dur­ing the term of this Agree­ment insur­ance cov­er­ages from insur­ers licensed or eli­gi­ble to do busi­ness in Flori­da and accept­able to the Dis­trict. The required insur­ance and min­i­mum lim­its are set forth in the Dis­trict ​’s Insur­ance Require­ments (Exhib­it A) attached to the Solic­i­ta­tion and incor­po­rat­ed herein.

To the fullest extent per­mit­ted by law, Con­trac­tor shall indem­ni­fy, defend, and hold harm­less the Dis­trict, its offi­cers, agents, and employ­ees (the ​“Indem­ni­fied Par­ties”) from and against any and all claims, lia­bil­i­ties, dam­ages, loss­es, and caus­es of action (includ­ing rea­son­able attor­neys’ fees and costs) aris­ing out of or result­ing from:

Bod­i­ly injury, death, or dam­age to prop­er­ty (includ­ing loss of use of prop­er­ty) caused by any neg­li­gent act or omis­sion of the Con­trac­tor, its employ­ees, sub­con­trac­tors, or agents in the per­for­mance of this Agree­ment; and/​or

Any fail­ure of the Con­trac­tor to com­ply with any applic­a­ble law, ordi­nance, or regulation.

Contractor’s indem­ni­fi­ca­tion oblig­a­tion includes defend­ing the Indem­ni­fied Par­ties in any legal or admin­is­tra­tive action, with coun­sel rea­son­ably accept­able to the Dis­trict, and pay­ing any final judg­ment or set­tle­ment that may be obtained against the Indem­ni­fied Par­ties. The Dis­trict shall prompt­ly noti­fy Con­trac­tor of any third-par­ty claim and, if the Dis­trict requests, Con­trac­tor shall assume con­trol of the defense; how­ev­er, the Dis­trict reserves the right to par­tic­i­pate in the defense at its own expense. Contractor’s indem­ni­ty shall not be lim­it­ed by any insur­ance cov­er­age or ben­e­fits. Any insur­ance main­tained by the Dis­tricts excess to Contractor’s insur­ance and indem­ni­ty obligations.

The covenants in this Sec­tion shall sur­vive ter­mi­na­tion or expi­ra­tion of this Agree­ment. If any claim or law­suit is brought against the Dis­trict that falls with­in the scope of Contractor’s indem­ni­ty, and Con­trac­tor fails to dili­gent­ly defend the Dis­trict, the Dis­trict may under­take its own defense and seek to recov­er from Con­trac­tor all costs and expens­es incurred in such defense.

To the extent (if any) an indem­ni­fi­ca­tion clause is lim­it­ed by §725.06 or §725.08, Flori­da Statutes, and if this Agree­ment is sub­ject to such statutes, then this indem­ni­fi­ca­tion is lim­it­ed to an amount of $1,000,000 or the amount of insur­ance required here­in (whichev­er is greater), and express­ly excludes the Dis­trict ​’s sole negligence.

9. FORCE MAJEURE

Nei­ther par­ty shall be liable for fail­ure to per­form its oblig­a­tions if such per­for­mance is pre­vent­ed or delayed by Force Majeure. For pur­pos­es of this Agree­ment, ​“Force Majeure” means an occur­rence that is beyond the rea­son­able con­trol of the par­ty affect­ed and could not have been avoid­ed by exer­cis­ing due care. Force Majeure events include, but are not lim­it­ed to: nat­ur­al dis­as­ters (e.g., hur­ri­canes, floods, earth­quakes), wars, acts of ter­ror­ism, epi­demics or pan­demics, labor strikes (exclud­ing strikes of a party’s own employ­ees), sab­o­tage, riots, or gov­ern­men­tal actions (e.g., emer­gency orders) that direct­ly pre­vent work. Upon the occur­rence of a Force Majeure event, the affect­ed par­ty shall prompt­ly noti­fy the oth­er par­ty in writ­ing, describ­ing the event and its impact on per­for­mance. The time for the affect­ed party’s per­for­mance shall be equi­tably extend­ed for the dura­tion of the Force Majeure delay, or if per­for­mance has become impos­si­ble, the par­ties will nego­ti­ate in good faith to amend or ter­mi­nate the Agreement.

If a Force Majeure event con­tin­ues for an extend­ed peri­od (e.g., more than 60 days) such that it frus­trates the pur­pose of the con­tract, the Dis­trict may ter­mi­nate the Agree­ment in whole or in part with­out penal­ty. Con­trac­tor is not enti­tled to extra com­pen­sa­tion for delays or increased costs caused by Force Majeure but Con­trac­tor shall be enti­tled to an exten­sion of time. Con­trac­tor must use best efforts to mit­i­gate the impacts of any Force Majeure (e.g., by secur­ing alter­nate sources or work-arounds where feasible).

No claim for exten­sion of time due to Force Majeure shall be valid unless the Con­trac­tor has noti­fied the Dis­trict in writ­ing with­in a rea­son­able time (not to exceed 5 days) after the onset of the Force Majeure event. Fail­ure to time­ly noti­fy con­sti­tutes waiv­er of any sched­ule adjust­ment. Rou­tine weath­er con­di­tions (oth­er than offi­cial­ly declared dis­as­ters) are typ­i­cal­ly not Force Majeure unless unusu­al­ly severe for the locale/​season and impact­ing the crit­i­cal path of performance.

10. TER­MI­NA­TION

10.1 District’s Right to Ter­mi­nate for Cause

The Dis­trict may ter­mi­nate this Agree­ment, in whole or in part, for cause upon writ­ten notice to Con­trac­tor if Con­trac­tor mate­ri­al­ly breach­es any term of the Agree­ment and fails to cure such breach with­in 7 cal­en­dar days (or such longer peri­od autho­rized in writ­ing by the Dis­trict) after receiv­ing writ­ten notice of the default from the Dis­trict. A mate­r­i­al breach by Con­trac­tor includes, but is not lim­it­ed to:

A. Fail­ure to per­form the work with suf­fi­cient labor, equip­ment, or mate­ri­als to meet required sched­ules or specifications;

B. Fail­ure to make pay­ment prop­er­ly to sub­con­trac­tors or sup­pli­ers for mate­ri­als or labor (cre­at­ing risk of claims/​liens);

C. Dis­re­gard of laws, ordi­nances, or instruc­tions of the District;

D. A mate­r­i­al mis­rep­re­sen­ta­tion by Con­trac­tor in its bid/​proposal or dur­ing con­tract performance;

E. Insol­ven­cy or fil­ing of bank­rupt­cy by Con­trac­tor; or

F. Any oth­er mate­r­i­al breach of Contractor’s oblig­a­tions under the con­tract documents.

In the event of ter­mi­na­tion for cause, the Dis­trict may take over the work and com­plete it through oth­er means, and Con­trac­tor shall be liable to the Dis­trict for all rea­son­able addi­tion­al costs incurred by the Dis­trict to com­plete the work (includ­ing the cost dif­fer­ence for obtain­ing sub­sti­tute per­for­mance and Dis­trict ​’s inter­nal costs). The Dis­trict may also with­hold any pay­ments due to Con­trac­tor for work per­formed pri­or to ter­mi­na­tion until the District’s dam­ages have been cal­cu­lat­ed and deduct­ed. If the unpaid bal­ance of the con­tract sum exceeds the cost of fin­ish­ing the work, any excess shall be paid to Con­trac­tor. If the District’s cost to com­plete exceeds the unpaid bal­ance, Con­trac­tor shall pay the dif­fer­ence to the District.

The District’s rights and reme­dies in this clause are cumu­la­tive and in addi­tion to any oth­ers pro­vid­ed by law or the con­tract. If it is lat­er deter­mined by a court or arbiter that the District’s ter­mi­na­tion for cause was wrong­ful or with­out basis, then the ter­mi­na­tion shall be deemed a ter­mi­na­tion for con­ve­nience, and Contractor’s rem­e­dy will be lim­it­ed to the com­pen­sa­tion described under Ter­mi­na­tion for Con­ve­nience below (and Con­trac­tor waives any oth­er dam­ages, includ­ing lost prof­its, in such scenario).

10.2 District’s Right to Ter­mi­nate for Convenience

Notwith­stand­ing any oth­er pro­vi­sion, the Dis­trict reserves the right to ter­mi­nate this Agree­ment, or any por­tion of it, at any time with­out cause by pro­vid­ing at least thir­ty (30) days’ writ­ten notice to Con­trac­tor. In such event, Con­trac­tor shall imme­di­ate­ly stop work on the date and to the extent spec­i­fied in the notice and place no fur­ther orders for mate­ri­als, ser­vices, or facil­i­ties except as nec­es­sary to com­plete any por­tion of work not ter­mi­nat­ed. Con­trac­tor shall also make every rea­son­able effort to can­cel or mit­i­gate any pend­ing orders or sub­con­tracts relat­ed to the ter­mi­nat­ed work.

In the event of a ter­mi­na­tion for con­ve­nience, the Dis­trict will pay Con­trac­tor for all work actu­al­ly per­formed up to the effec­tive date of ter­mi­na­tion (includ­ing mate­ri­als or equip­ment deliv­ered and in tran­sit that can­not be can­celed), at the con­tract prices, and for all demo­bi­liza­tion costs and oth­er rea­son­able costs incurred as a direct result of the ter­mi­na­tion (such as can­cel­la­tion fees owed to sub ven­dors). How­ev­er, Con­trac­tor shall not be enti­tled to any lost prof­its or antic­i­pat­ed prof­its on the por­tion of work that was not per­formed due to ter­mi­na­tion, nor to any con­se­quen­tial dam­ages. The com­pen­sa­tion for a ter­mi­na­tion con­ve­nience will be lim­it­ed to: pay­ment for accept­able work per­formed, plus rea­son­able costs of set­tling and pay­ing any claims from sub­con­trac­tors and sup­pli­ers for actu­al work per­formed (which were not already paid for), plus a rea­son­able allowance for over­head and prof­it on the work per­formed, not to exceed the con­tract price allo­ca­tion for that work. Con­trac­tor must sub­mit its ter­mi­na­tion claim with­in 30 days after receipt of the ter­mi­na­tion notice (absent agree­ment of extension).

The Dis­trict may, at its dis­cre­tion, direct Con­trac­tor to assign to the Dis­trict any sub­con­tracts or pur­chase orders for mate­ri­als that the Dis­trict choos­es to retain for com­ple­tion of the project. Any mate­ri­als or equip­ment paid for by the Dis­trict shall become the Dis­trict ​’s property.

10.3 Con­trac­tor Right to Terminate

Con­trac­tor may ter­mi­nate this Agree­ment for cause if the Dis­trict mate­ri­al­ly breach­es its oblig­a­tions, such as fail­ing to pay undis­put­ed amounts due with­in 60 days after writ­ten notice from Con­trac­tor of delin­quen­cy, pro­vid­ed Con­trac­tor has giv­en the Dis­trict at least 30 days’ pri­or writ­ten notice of such breach and an oppor­tu­ni­ty to cure. Con­trac­tor may also ter­mi­nate if work is stopped for 90 days through no fault of Con­trac­tor due to a court order or sub­stan­tial fail­ure of the Dis­trict to per­form. Con­trac­tor’ ter­mi­na­tion must be by writ­ten notice to the Dis­trict. In such event, Con­trac­tor shall be com­pen­sat­ed in the same man­ner as a ter­mi­na­tion for con­ve­nience (as Con­trac­tor sole rem­e­dy), and no antic­i­pa­to­ry prof­it or con­se­quen­tial dam­ages may be claimed.

10.4 Sus­pen­sion of Work

As dis­tinct from ter­mi­na­tion, the Dis­trict may at any time sus­pend the work in whole or in part for its con­ve­nience by pro­vid­ing writ­ten notice to Con­trac­tor. Con­trac­tor shall imme­di­ate­ly com­ply with the sus­pen­sion order and prop­er­ly secure and pro­tect the work­site. The Dis­trict shall allow a rea­son­able exten­sion of time for the sus­pen­sion and, if the sus­pen­sion lasts more than six­ty (60) days, shall equi­tably adjust com­pen­sa­tion to cov­er the cost of maintaining/​suspending work (exclud­ing prof­it). When the Dis­trict so directs, Con­trac­tor shall resume work prompt­ly. If work is sus­pend­ed for 120 days or more (aggre­gate) through no fault of Con­trac­tor, Con­trac­tor may treat it as a ter­mi­na­tion for convenience.

11. WAR­RAN­TY AND COR­REC­TION OF WORK

Con­trac­tor war­rants that all goods, mate­ri­als, and equip­ment pro­vid­ed under this Agree­ment shall be new, free of defects in title, mate­ri­als, and work­man­ship, and shall con­form to the require­ments of the con­tract doc­u­ments (includ­ing any sam­ples or spec­i­fi­ca­tions). Con­trac­tor fur­ther war­rants that all ser­vices (includ­ing instal­la­tion or con­struc­tion work) shall be per­formed in a skilled and work­man­like man­ner con­sis­tent with the stan­dards of the indus­try. All work shall be of good qual­i­ty, free from faults and defects, and in strict con­for­mance with the contract.

This war­ran­ty extends for the peri­od spec­i­fied in the Solic­i­ta­tion or Tech­ni­cal Spec­i­fi­ca­tions; if no peri­od is spec­i­fied, then for a min­i­mum of one (1) year from the date of final accep­tance of the work or from dis­cov­ery of the defect, whichev­er is lat­er. For latent defects or fraud, the war­ran­ty peri­od shall not bar Dis­trict ​’s legal rights.

If any por­tion of the goods or work does not con­form to the require­ments of this Agree­ment or is found to be defec­tive with­in the war­ran­ty peri­od, the Dis­trict shall noti­fy Con­trac­tor in writ­ing. Con­trac­tor shall, at its own expense and direc­tion of the Dis­trict, prompt­ly cor­rect, repair, or replace the defec­tive or non-con­form­ing item or work. If repair or replace­ment is not fea­si­ble, the Dis­trict may require an appro­pri­ate equi­table adjust­ment in price or may pro­cure sub­sti­tute goods/​services and charge the cost to Con­trac­tor. If Con­trac­tor fails to rem­e­dy any such defect with­in a rea­son­able time after notice, the Dis­trict has the right to per­form or pro­cure such rem­e­dy and Con­trac­tor shall reim­burse the Dis­trict for the cost. Alter­na­tive­ly, the Dis­trict may elect to accept defec­tive or non-con­form­ing work and reduce the price accord­ing­ly. The war­ran­ty on any repaired or replaced work shall extend for an addi­tion­al war­ran­ty peri­od (e.g., one year) from the date of accep­tance of the repair replacement.

Con­trac­tor shall assign to the Dis­trict (or enforce on the Dis­trict ​’s behalf) any manufacturer’s war­ranties for equip­ment or mate­ri­als pro­vid­ed, to the extent such war­ranties are assign­a­ble. Con­trac­tor shall coop­er­ate with the Dis­trict in pur­su­ing war­ran­ty claims against man­u­fac­tur­ers. This war­ran­ty is in addi­tion to any oth­er rights or reme­dies avail­able to the Dis­trict under this Agree­ment or law. Accep­tance of the work by the Dis­trict shall not relieve Con­trac­tor of its war­ran­ty obligations.

12. ASSIGN­MENT

This Agree­ment may not be assigned.

13. SEV­ER­ABIL­I­TY

In the event any pro­vi­sion of this Agree­ment shall be held invalid or unen­force­able by any court of com­pe­tent juris­dic­tion, such hold­ing shall not inval­i­date or ren­der unen­force­able any oth­er pro­vi­sion hereof.

14. MOD­I­FI­CA­TIONS

No mod­i­fi­ca­tion, change order, or amend­ment to this Agree­ment is effec­tive unless it is in writ­ing and exe­cut­ed by both par­ties with the same for­mal­i­ty as this Agree­ment. The Dis­trict may, how­ev­er, uni­lat­er­al­ly order minor changes in the work not involv­ing an adjust­ment in price or time, con­sis­tent with the intent of the con­tract doc­u­ments (such changes shall be con­firmed in writing).

The Dis­trict reserves the right to make changes to the scope of work, includ­ing addi­tions, dele­tions, or oth­er revi­sions. If any such change caus­es an increase or decrease in the Contractor’s cost or time required for per­for­mance, an equi­table adjust­ment in con­tract price or time will be made and incor­po­rat­ed by writ­ten change order. Con­trac­tor shall prompt­ly noti­fy the Dis­trict if any Dis­trict-direct­ed change (or oth­er cir­cum­stance) will affect cost or time, and sub­mit sup­port­ing doc­u­men­ta­tion. No claim for addi­tion­al com­pen­sa­tion or time shall be valid unless autho­rized in writ­ing by the Dis­trict through a duly exe­cut­ed change order by the Dis­trict Exec­u­tive Direc­tor before the work is per­formed, except as oth­er­wise allowed by law.

If the Dis­trict and Con­trac­tor can­not agree on the amount of an adjust­ment, the Dis­trict may uni­lat­er­al­ly issue a change order reflect­ing its best esti­mate of the equi­table adjust­ment, and Con­trac­tor shall pro­ceed with the changed work. Con­trac­tor retains the right to pur­sue a claim under the dis­putes pro­vi­sion if it dis­agrees with the Dis­trict ​’s adjust­ment. Pend­ing res­o­lu­tion, Con­trac­tor must con­tin­ue performance.

Con­trac­tor shall not per­form any work or fur­nish any mate­ri­als out­side the scope of the Agree­ment unless pre-autho­rized in writ­ing by the Dis­trict. Work per­formed with­out prop­er autho­riza­tion is done at the Contractor’s own risk and the Dis­trict may refuse to pay for such work.

15. WAIV­ER

Fail­ure by the Dis­trict to enforce any pro­vi­sion of this Agree­ment shall not be deemed a waiv­er of the pro­vi­sion or mod­i­fi­ca­tion of this Agree­ment. A waiv­er by the Dis­trict of any breach of a pro­vi­sion of this Agree­ment shall not be deemed a waiv­er of any sub­se­quent breach and shall not be con­strued to be a mod­i­fi­ca­tion of the terms and con­di­tions of this Agreement.

16. ATTORNEY’S FEES AND VENUE

In the event of any lit­i­ga­tion, arbi­tra­tion, or medi­a­tion aris­ing from or relat­ing to this Agree­ment, the pre­vail­ing par­ty shall be enti­tled to recov­er its rea­son­able attor­neys’ fees and costs from the non-pre­vail­ing par­ty, includ­ing fees and costs incurred at the tri­al, appel­late, and post-judg­ment col­lec­tion lev­els. This pro­vi­sion is applic­a­ble to any pro­ceed­ing whether sound­ing in con­tract, tort, or statute. For pur­pos­es of this Agree­ment, ​“pre­vail­ing par­ty” means the par­ty that sub­stan­tial­ly obtains or defeats the relief sought, as deter­mined by the court or oth­er tri­bunal hav­ing juris­dic­tion. If each par­ty pre­vails on some aspect of the dis­pute, the attor­neys’ fees and costs shall be appor­tioned by the court/​tribunal in a fair manner.

The par­ties stip­u­late and agree that any and all claims, demands, actions or suits what­so­ev­er, aris­ing under this Agree­ment shall be sub­ject­ed to the sole and exclu­sive juris­dic­tion and venue of the 14th Judi­cial Cir­cuit in and for Bay Coun­ty, Florida.

17. NOTICES

Any notice required by this Agree­ment shall be direct­ed to the par­ties as follows:

As to District:

Dis­trict Rep­re­sen­ta­tive: Park­er W. McClel­lan, Jr.

Title/​Position: Exec­u­tive Director

Address: 6300 West Bay Park­way, Box A, Pana­ma City, FL 32409

Phone: 850−636−8950

As to Contractor:

Con­tract Rep­re­sen­ta­tive: Brad­ford Dove, P.E.

Title/​Position: Vice Pres­i­dent – Civ­il Operations

Email Address: bdove@​morgan1.​com

Mail­ing Address: 900 Dutch Val­ley Dr. Knoxville, TN 37918

Phone: 865−249−8640

18. ENTIRE AGREEMENT

This Agree­ment, and any exhibits or appen­dix­es attached here­to and incor­po­rat­ed here­in, con­sti­tutes the entire agree­ment between par­ties per­tain­ing to the sub­ject mat­ter here­of, and super­sedes all pri­or and con­tem­po­ra­ne­ous agree­ments, under­stand­ings, nego­ti­a­tions, and dis­cus­sions of the par­ties, whether oral or writ­ten, and there are no rep­re­sen­ta­tions, war­ranties, covenants or oth­er agree­ments among the parties.

The term ​“Agree­ment” means and includes the fol­low­ing doc­u­ments, all of which are incor­po­rat­ed into this Agree­ment by reference:

➢ Exhib­it A – Contractor’s Bid Schedule

➢ Exhib­it B – Con­formed Tech­ni­cal Specifications

➢ Exhib­it C – Invi­ta­tion to Bid Documents

• ITB-2026 – 14 Bid Package

• ITB-2026 – 14 FAA Requirements

• ITB-2026 – 14 Bid Schedule

• ITB-2026 – 14 Adden­dum No.1

➢ Exhib­it D – Con­trac­tors Bid

➢ Exhib­it E – Insur­ance Requirements

➢ Exhib­it D – Con­trac­tor Bonds

➢ Exhib­it F – AIP Grant Appli­ca­tion and sub­se­quent Grant Agreement

➢ Exhib­it G – ECP Stan­dard Terms and Conditions

➢ Exhib­it H – Fed­er­al­ly Required Con­tract Provisions

➢ Exhib­it I – Con­formed Plans

Note: With­in the drawings/​specs: fig­ured dimen­sions gov­ern over scal­ing; large-scale details gov­ern over small-scale; and the Con­trac­tor shall not rely on scale where dimen­sions are given.

Con­tract Doc­u­ments; Order of Prece­dence. The ​“Con­tract Doc­u­ments” con­sist of the exe­cut­ed Agree­ment (Sec­tion 00050), all exhibits to the Agree­ment, the Solic­i­ta­tion (includ­ing the tech­ni­cal spec­i­fi­ca­tions and draw­ings), all adden­da issued before bid open­ing, and all oth­er doc­u­ments express­ly incor­po­rat­ed by ref­er­ence. These Con­tract Doc­u­ments are intend­ed to be com­ple­men­tary. If a con­flict or incon­sis­ten­cy exists, the fol­low­ing order of prece­dence gov­erns (high­est to lowest):

1. Writ­ten Change Orders and writ­ten amend­ments exe­cut­ed by the Dis­trict (most recent first);

2. The exe­cut­ed Agree­ment (Sec­tion 00050) and its exhibits (includ­ing insurance/​bonding forms);

3. Adden­da issued by the Dis­trict pri­or to bid opening;

4. ECP Terms and Conditions;

5. Fed­er­al­ly Required Con­tract Provisions;

6. Bid Pro­pos­al Form and the Contractor’s bid pric­ing sched­ule (for pric­ing only).

7. The Dis­trict ​’s Stan­dard Terms and Con­di­tions for Bidding.

8. The AIP Grant issued by FAA to pro­vide financ­ing for the Project.

IN WIT­NESS WHERE­OF, the Con­trac­tor has exe­cut­ed this Agree­ment as of the day and year writ­ten below.

MOR­GAN CON­TRACT­ING, INC. PANA­MA CITY – BAY COUN­TY AIRPORT

a Flori­da for Prof­it Cor­po­ra­tion AND INDUS­TRI­AL DISTRICT

a spe­cial dis­trict of Florida

By: By:

Brad­ford Dove, P.E. William C. Cramer, III, Chair

Date: _______________________________ Date:

Remain­der of Page Inten­tion­al­ly Left Blank