Pre-Proposal Non-Mandatory Zoom Meeting for Engineering Services RFQ Q&A, Physical Site Tour Date, and Other Q&A
Zoom Meeting Attendees, Dec. 3, 2020
ECP Airport Staff Present:
Parker McClellan, Executive Director
Richard McConnell, Deputy Executive Director
Kathy Gilmore, Executive Assistant
Zoom Attendees:
David Scruggs, ZHA
Laura Saunders, Maser Consulting
Mark Kistler, Michael Baker International
Justin Edwards, Infrastructure Consulting & Engineering (ICE)
Kelly Darby-Asher, Fitzgerald Collaborative
Shanna Miller, Fitzgerald Collaborative
Q&A during Zoom Meeting Dec. 3, 2020
Submitted by: Justin Edwards, Infrastructure Consulting & Engineering (ICE)
Q: Will the recent FDOT regulation requiring engineering to be done by one firm and construction inspection to be done by another come into play and will you select more than one consultant because of that?
A: We have a separate contract for Construction Engineering & Inspection (CEI) already, good for another year, and then we will go out for another CEI to keep that clean and separate.
Submitted by: Laura Saunders, Maser Consulting
Q: Is there a current firm you have a contract with?
A: Yes: ZHA out of Orlando
Submitted by: Mark Kistler, Michael Baker International
Q: Will the project list continue to evolve?
A: Yes: we are just finishing up our Master Plan and it is quite possible some of the projects may change, but that is what we have today. The Master Plan Update is being done by CHA Consulting, Inc.
Submitted by: Shanna Miller, Fitzgerald Collaborative
Q: How many copies of the proposal do we need to submit?
A: One original, four copies, and one electronic version. The original is for our record copy. Four copies because we will have four on the evaluation team. The evaluation team will include Parker McClellan, Executive Director; Richard McConnell, Deputy Executive Director; Darlene Nelson, Director of Finance and Administration; and Del Lee, immediate Past Chairman of the Board and current Board Member. I remind everyone there is a cone of silence, so they should direct you to submit your questions to info@pcairport.com.
Submitted by: Justin Edwards, Infrastructure Consulting & Engineering (ICE)
Q: Are you planning to have a host tour so we can see the airport?
A: A physical site tour has been scheduled for Thursday, Dec. 10, at 9:30 a.m. (CST). The tour will be conducted within established health guidelines. It is anticipated the tour will not take more than one hour. Please meet at the first floor Information Desk in the Terminal.
Submitted by: Laura Saunders, Maser Consulting
Q: Please clarify the difference between the current firm that has this contract, and the firm doing the Master Plan Update.
A: They are two separate companies. ZHA has been our general engineering consultant for the last ten years. CHA is doing our Master Plan Update.
Submitted by: Shanna Miller, Fitzgerald Collaborative
Q: Is there a page limit on the proposal?
A: Although not required, it is anticipated the Statement of Qualifications should not exceed 30 pages (does not include required Certification Forms).
Submitted by: Justin Edwards, Infrastructure Consulting & Engineering (ICE)
Q: Can I request the callers identify themselves?
A: The Zoom attendees identified themselves (see list above)
Questions via info@pcairport.com
Submitted by: Joe Di Stefano, Tierra, Inc., Dec. 3, 2020
Q: Can I get a listing of attendees for the virtual meeting that was held for this project earlier today?
A: See attendee list above.